*The Feakle Rd in Ballyminoge in Scariff. Photograph: Ruth Griffin

SCARIFFโ€™s planned social housing scheme has met an early hiccup with the construction date delayed.

Although it was stated by Clare County Councilโ€™s Director of Social Development which has responsibility for housing, Anne Haugh at the November meeting of the Killaloe Municipal District that construction on the โ‚ฌ6m social housing scheme in Scariff would commence before Christmas with the Department of Housing putting pressure on Councils not to delay projects. She has now confirmed that the December start on site will not happen.

Speaking at Mondayโ€™s meeting of the County Council, Ms Haugh admitted that โ€œpost-tender administrationโ€ had delayed the planned start. She said that the Council now intends to award the contract for the proposed eighteen unit development in January and complete the signing in the New Year.

This โ€œpost-tender administrationโ€ is the legal checks associated carried out by the Council on the prospective tender, The Clare Echo understands.

Cllr Pat Burke (FG) told The Clare Echo, โ€œIโ€™m disappointed with the delay, we were led to believe back in the summer that things would be well underway by nowโ€.

With the one month delay from December 2022 to January 2023, the local authority will still work towards its targeted completion date of the first quarter of 2024.

Developments carried out by local authorities are often referred to as โ€˜Part 8 developmentsโ€™ which is in reference to Part 8 of the Planning and Development Regulations 2001, as amended, which sets out the procedure for carrying out such developments. Such works would include developments such as the construction of houses, roads, swimming pools, public toilets and more.

Part 8 approval has been granted for the Scariff social housing scheme with the tender assessment for construction complete.

At the Killaloe MD meeting last month, the Director detailed that the successful tender had been notified.

Clare County Council in November 2020 lodged plans for the scheme which will be called โ€˜Droichead Nuaโ€™ and will be located at the Feakle Road in Ballyminoge, Scariff. Stage three approval was granted for the development in July of this year by the Department of Housing, Local Government and Heritage. Approval was granted with an all-in budget of โ‚ฌ6,093,289 including VAT in July.

Fourteen apartments, twelve of which will have two bedrooms will make up the development which will also have two semi-detached, two-storey, three-bedroom houses, with adaptations.

Related News

rachael english 1
Rachael staying put on Radio One following reshuffle
IMG_1935
โ€œWe're survivorsโ€ - Pink currach spreads awareness on cancer
shane flanagan 1
Ennis man serving seven years for inciting rape of fellow Garda pleads guilty to PULSE disclosure
9e58eacc-fad7-4f29-9c76-049e0d6201a1
Killaloe bodybuilder goes international
Latest News
shane flanagan 1
Ennis man serving seven years for inciting rape of fellow Garda pleads guilty to PULSE disclosure
inagh kilnamona v clooney:quin u21 26-10-25 evan maxted jack mescall 4
Wet & wild winning U21 starts for Inamona, Cratloe, ร‰ire ร“g & Sixmilebridge
patsy cronin gerry moloney 1
Stalwarts Cronin & Stud Moloney honoured
9e58eacc-fad7-4f29-9c76-049e0d6201a1
Killaloe bodybuilder goes international
mick o'dea-2
Honorary doctorate from DCU for Ennis artist Mick O'Dea
Premium
Avenue Utd collect first silverware of season with Hugh Kelly Cup success
Inagh/Kilnamona exit Munster at first hurdle losing to Newcastle West
Six year driving ban for Ennis man who refused to provide sample to Gardaรญ
Shannon meat operator pays out โ‚ฌ2k debt to supplier
Extra time defeat 'not the end' of Truagh/Clonlara

Advertisement

Subscribe for just โ‚ฌ3 per month

If youโ€™re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just โ‚ฌ3 a month (less than 75c per week), and thereafter โ‚ฌ8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.