Keating Construction have yet to inform clients including Clare County Council if they will be able to complete works on ongoing projects.

Workers belonging to the marine, civil engineering and building company have not returned on-site at ongoing developments for over seven days, two locations in question include the University of Limerick and where the new Ennis Library is to be built.

No information has been forthcoming from Keating in relation to its future outlook. Its headquarters in Kilmihil have also remained closed. Employees are not optimistic and The Clare Echo understands an announcement is expected in the coming days.

Late 2021 was the original target for the finishing of the library which has a price tag close to €14m. The onset of COVID-19 and temporary pause of construction work for two months was envisaged to have delayed works and set the completion of works back into the first half of 2022.

An update was sought by Cllr Pat Daly (FF) at Monday’s meeting of Clare County Council with regards to the stoppage of works by glór. “It’s a serious situation that needs to be rectified in the very immediate future. It’s important that a replacement building contractor should be appointed in the very near future. It shouldn’t be drawn out for 12 months”.

Chief Executive of the local authority, Pat Dowling replied by saying their focus remained on financing and commissioning the completion of the project. “We are continuing to engage with our suppliers and sub contractors in relation to commissioning and certifying the works, that commitment remains and should there be any change on that members, I will let you know immediately”.

Dowling continued, “We’ve had to deal with a national crisis in the last few months, we will deal with this also if it arises and proceed with an alternative route, for now that is the stance on it”.

Shannon representative, Cllr Gerry Flynn (IND) was adamant there would be “a time lapse” despite the non-committal remarks from the Chief Executive.

“Nothing has been confirmed that works will be discontinued,” Dowling responded. He warned that there is a potential of an extra twelve months being added on meaning the finish date would be pushed to 2023. “If there is a change, there is a delay,” he cautioned.

Related News

st marys church ruan 29-04-26 4
Timber spire restored to Ruan church as refurbishment continues following lightning strike
The Armada Hotel, Spanish Point
Armada's €1.5m plans for water pipeline splits opinion in Spanish Point & Quilty
guy flouch 1-2
European Youth week event in Ennis to showcase options to study abroad
fire kilkee bus 1
No injuries after bus bringing Kilkee students on tour catches fire
Latest News
emma downey 2
Meelick's Emma in running to be named winner of Miss Ireland Teen
emma deeegan
Tulla Utd trying to take back crown of Cup champions
hermitage 19-03-26 2
Proposals afoot to bring in cul-de-sac to Hermitage
st marys church ruan 29-04-26 4
Timber spire restored to Ruan church as refurbishment continues following lightning strike
clare vs waterford minor 24-04-26 ger o'connell cian mullins 1
Clare minor hurlers embracing must-win territory to keep season alive
Premium
Proposals afoot to bring in cul-de-sac to Hermitage
Timber spire restored to Ruan church as refurbishment continues following lightning strike
Clare minor hurlers embracing must-win territory to keep season alive
Armada's €1.5m plans for water pipeline splits opinion in Spanish Point & Quilty
Davy Mc back in the mix for Clare hurlers

Annual Subscription!

The Clare Echo annual subscription for just €69.99 a year. 

Prefer to pay monthly? Click the monthly option and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. 

Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.