Keating Construction have yet to inform clients including Clare County Council if they will be able to complete works on ongoing projects.

Workers belonging to the marine, civil engineering and building company have not returned on-site at ongoing developments for over seven days, two locations in question include the University of Limerick and where the new Ennis Library is to be built.

No information has been forthcoming from Keating in relation to its future outlook. Its headquarters in Kilmihil have also remained closed. Employees are not optimistic and The Clare Echo understands an announcement is expected in the coming days.

Late 2021 was the original target for the finishing of the library which has a price tag close to €14m. The onset of COVID-19 and temporary pause of construction work for two months was envisaged to have delayed works and set the completion of works back into the first half of 2022.

An update was sought by Cllr Pat Daly (FF) at Monday’s meeting of Clare County Council with regards to the stoppage of works by glór. “It’s a serious situation that needs to be rectified in the very immediate future. It’s important that a replacement building contractor should be appointed in the very near future. It shouldn’t be drawn out for 12 months”.

Chief Executive of the local authority, Pat Dowling replied by saying their focus remained on financing and commissioning the completion of the project. “We are continuing to engage with our suppliers and sub contractors in relation to commissioning and certifying the works, that commitment remains and should there be any change on that members, I will let you know immediately”.

Dowling continued, “We’ve had to deal with a national crisis in the last few months, we will deal with this also if it arises and proceed with an alternative route, for now that is the stance on it”.

Shannon representative, Cllr Gerry Flynn (IND) was adamant there would be “a time lapse” despite the non-committal remarks from the Chief Executive.

“Nothing has been confirmed that works will be discontinued,” Dowling responded. He warned that there is a potential of an extra twelve months being added on meaning the finish date would be pushed to 2023. “If there is a change, there is a delay,” he cautioned.

Related News

Trump-Golf-Hotel-50
Trump Doonbeg unable to restore conditions for tiny snail
marie donnellan 1
Marie always remembers Catherine with release of new children's book
21042026_Council__Busstops_0112
Start of Ennis town bus service pushed back again
Screenshot
Two decades of false starts & hundreds of objections later - Galway City Ring Road gets go ahead
Latest News
Trump-Golf-Hotel-50
Trump Doonbeg unable to restore conditions for tiny snail
paul geaney 2
'All of our trips to Cusack Park are testing' says Kerry's Geaney
kerry v clare 06-01-26 ikem ugwueru 3
Clare & Kerry name sides for Munster semi-final
marie donnellan 1
Marie always remembers Catherine with release of new children's book
clare v fermanagh 15-02-26 paul madden 1
'If you are not excited about playing the All-Ireland champions you shouldn't be in the dressing room' - Madden ready for biggest managerial test
Premium
'All of our trips to Cusack Park are testing' says Kerry's Geaney
'If you are not excited about playing the All-Ireland champions you shouldn't be in the dressing room' - Madden ready for biggest managerial test
Rouine exits Clare panel ahead of Munster semi-final
Start of Ennis town bus service pushed back again
Emmet nearing a return to action but Munster campaign will come too soon

Annual Subscription Offer NOW ON!

The Clare Echo has launched a discounted annual subscription for just €39.99 a year. 

Prefer to pay monthly? Click the monthly option and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. 

Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.