*Flooding in Clareabbey. Photograph: Joe Buckley

An estimated €20m is being spent on flood defences projects in the Ennis Municipal District while ongoing concerns regarding the structural stability of the Clarecastle Flood Barrage have been raised.

Construction on the Ennis South Flood Relief Scheme began in March 2019 and is scheduled for completion in August 2021. The Ennis Lower Scheme at Harmony Row has recently commenced with other schemes on the agenda including Thomond Villas in Clarecastle and Shalee Drive/Victoria Court in Ennis.

€20m alone is the estimated total budget for the South Flood Relief Scheme. Construction costs of €14.3m along with land costs, design, advance work, supervision, archaeology and contingency plus “a reserve for future operational and maintenance costs” form the bill, senior engineer with Clare County Council Seán Lenihan outlined.

Flooding at St Flannan’s College and surrounding areas, Ballybeg and the Clare Abbey flood plain will be dealt with under the scheme. It has three elements, the St Flannan’s culvert, the Ballybeg culvert and the flood defence to the section of the River Fergus from Doora Bridge on the Quin Rd to the N85 Bridge at Clareabbey. The first two elements of the scheme are now complete “with only minor snags remaining to be addressed”.

Sheet piling work on the riverbank defence is “ninety five percent complete” but “seasonal environmental constraints” will prevent work on the pump station and landscaping from progressing until April.

April 2021 is earmarked as the completion for the Ennis Lower Flood Relief Scheme which has a calculated cost of €400,000. The final part of the scheme in mid-winter and extends from the Club Bridge to Bank Place on to the opposite side of the river to the Abbey St car park. Flooding risks will be mitigated by a sheet piled wall which “will be clad in stone on the riverside and capped in cut stone creating a nice vista”.

Development of a flood relief scheme for Thomond Villas in Clarecastle will be done by Malachy Walsh & Partners. The development includes construction of embankments and walls with an expected fee of €400k. “Significant environmental challenges” lay in the Council’s path, Lenihan advised as the proposed works are located near a Special Area of Conservation and a Special Protection Area.

Funding applications have been made to the Office of Public Works (OPW) to take the scheme to detailed design and planning stage. The Council has also applied to the OPW for funding to carry out a feasibility study over two years for two areas in Ennis town, Shalee Drive and Victoria Court. A hydrologist will have to be appointed to conduct the study.

Necessary funding is also to be sourced by the local authority “to carry out a high level assessment of the Barrage at Clarecastle,” Lenihan stated.

Cllr Johnny Flynn (FG) has committed to continue lobbying for the relocation of the Clarecastle flood barrage. “The sea tides come all the way up Shannon Estuary up to the Fergus Estuary but is held back with the coastal flood barrage at Clarecastle”. He raised concerns surrounding the “structural stability” of the Barrage and “its ability to deal with rising sea levels which are way in excess of what it was designed to in last century. If it collapsed it would I believe overwhelm all the flood defences in Ennis at time of high sea level and high rainfall”.

Senior engineer in the Ennis MD, Eamon O’Dea detailed than a company has been engaged to do a structural survey of the Barrage with work to be undertaken on the foundation to its doors in the Spring time.

Flynn added that when the Ennis Lower Flood Relief Scheme is completed it will mean a figure in the region of €40m would have been spent on flood defences along the River Fergus from the Gort Rd all the way to Clarecastle.

Related News

Clare Pyrite Action Group Meeting at Treacy's West County Hotel-9294
Ex-TD, Violet Anne Wynne now owes €5,350 to ex-employee as judge monitors payments from €11,500 WRC award
160A8707
St Flannans to meet St Josephs in Harty Cup semi-final
160A8326
St Josephs through to Harty Cup hurling semi-final
pexels-robshumski-1903707
Yellow warning with 53km/h winds to hit Clare over the weekend
Latest News
160A8326
St Josephs through to Harty Cup hurling semi-final
pexels-robshumski-1903707
Yellow warning with 53km/h winds to hit Clare over the weekend
ryan griffin conor finnucane mikey o'neill matt shea 1
Lissycasey look to championship winning selector & ex Clare footballers in bid to make breakthrough
éire óg v kilmaley 20-09-25 brian culbert 2
Culbert going back for year four with Kilmaley
Gemma Hayes-by Charlotte (@underthefeather) (1)
Resonance Festival reveals 2026 line-up and February dates
Premium
Culbert going back for year four with Kilmaley
Donagh back for fifth season with beaten finalists Doora/Barefield
Narrow defeat for Clare against All-Ireland champs Kerry
Cullinan making comeback as Inagh/Kilnamona manager
Tommy Tiernan helps object to now withdrawed €1.4bn off-shore windfarm

Subscribe for just €3 per month

If you’re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.