https://clareecho.ie/

ASSURANCES HAVE BEEN issued for the future of the Killaloe Bridge and Bypass project.

Approval was granted for the project in December by Minister for Transport, Eamon Ryan (GP) when he gave Clare County Council the thumbs up to award the contract for the €43.7m Killaloe Bypass, River Shannon Crossing and upgrade of the R494 project to John Sisk & Son. The cost of the project has now risen substantially.

A letter of acceptance was issued to the construction company on February 16th 2022. Seán Lenihan, senior engineer in the Project Management Office of Clare County Council explained, “they were essentially in contract as of March 16th 2022 with works allowed to start on site anytime thereafter. The contract period is for 33 months,” and the start date will be decided by Sisk.

Speaking on Monday, he quelled fears that Sisk have withdrawn from the project and that Department funding was pulled. The letter of acceptance and Chief Executives order formally appointing RPS Consulting Engineers as consultant to provide site supervisory roles and engineering staff “has been prepared and will be issued once we have the main contractors detailed construction programme to hand”.

In the May edition of the Council’s monthly management report, Lenihan outlined, “We are all aware of the issues affecting the construction industry generally with hyper-inflation driving up costs significantly, unprecedented supply chain difficulties due to Brexit, the Ukrainian conflict, economic sanctions applied against Russia and more recently, regrettably the fallout from the Roadbridge receivership and the combined effect of these has hindered the commencement of the works on site”.

Programme sequencing is under review to try facilitate alternative procurement strategies to secure the supply chain and manage inflationary risk. Lenihan said they are working closely with Sisks to progress the project “at the earliest juncture” but conceded, “while the resequencing of some works may assist with Sisks commencement on site, it will not address the significant cost escalations since the works were priced late last year”.

Current works ongoing related to the project include remaining land acquisitions, ecological monitoring of the bat roost structure and reports into the yet to be received results to the testing and carbon dating analysis of archaeological items uncovered during the investigation works carried out on site in 2021.

At the May meeting of the Council, Cllr Pat Burke (FG) sought “further assurance” that the project was “on track”. He commented, “the report is positive but we’re a bit concerned on the ground”.

Lenihan referenced the pressures faced by the construction sector presently, “our project is no different”. He revealed that concerns exist regarding the price issued in last August compared with the current-day figure. “We are in negotiations with Sisk, to allay any rumours Sisk have not withdrawn and the Department have not pulled the funding”.

Related News

jessica o'gorman
Newmarket-on-Fergus jockey nominated for award
simon harris joe cooney 21-11-25 6
Tánaiste praises Kilkishen's community spirit as he switches on Christmas lights
bothár na rinne 19-11-25 1
Bóthar na Rinne left 'in a bad state'
cian crimmins 1
Crimmins wins rising star in business award
Latest News
st finbarrs vs éire óg 23-11-25 mark mcinerney 1
Brilliant Barrs eliminate Éire Óg footballers to end Munster double dream
corofin v an ghaeltacht 23-11-25 brian ó beaglaíoch diarmuid cahill 1
Corofin come up short against An Ghaeltacht
ennistymon v clondegad 23-11-25 joshua vaughan james cullinan 1
Ennistymon win U21A title for fourth time
clooney:quin vs broadford:bodyke 11-10-25 9
Clooney/Quin unable to go to The Well in Munster junior final
bothár na rinne 19-11-25 1
Bóthar na Rinne left 'in a bad state'
Premium
Ennistymon win U21A title for fourth time
Clooney/Quin unable to go to The Well in Munster junior final
Clare's Oscar Traynor campaign concludes with defeat to Limerick
Tánaiste says another hospital is needed in Mid-West & that Ennis has been 'under-utilised'
Exciting U21A final expected between Ennistymon & Clondegad

Subscribe for just €3 per month

If you’re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.