CLARE County Council could face a funding shortfall of more than €2m for its 2027 roads programme if additional Government funding is not secured, councillors have been warned.
The issue was raised during the statutory budget meeting of Clare County Council, where elected members questioned how the local authority would manage rising road maintenance costs and whether funding would be sufficient to repeat the full programme of work carried out in 2026.
Director of Finance, Investment and Enterprise Noeleen Fitzgerald said the Council would not know its Specific Improvement Grant allocation until January, meaning it could not yet establish whether funding would be at a similar level to this year.
She warned that if the necessary grant funding was not received, there could be a “pretty significant” impact on next year’s programme, with more than €2m potentially needing to be taken out.
Cllr Pat Hayes (FF) said the budget highlighted the financial pressures facing the Council, particularly in relation to inflation and the rising cost of roadworks. He questioned how the local authority would manage the increasing costs, warning that there was a “real crisis coming here”.
Cllr Hayes said there was an urgency to secure additional funding for the roads department and called for a formula to be found to provide more resources. He also questioned how the Council would finance its programme if Government road grants did not increase in line with inflation.
Ms Fitzgerald said the Council had factored in an increased allocation for roads in the 2027 budget, but there was still uncertainty around the level of Government funding it would receive.
Cllr Pat O’Gorman (FF) also raised concerns about the roads allocation, referring to an overspend of approximately €2m on the 2026 programme and asking whether the Council could expect the same level of funding again. He said the €212m budget was “some budget to try and balance” and acknowledged that commercial rates would not increase, but questioned how the potential funding gap would be addressed.
Cllr Pat Burke (FG) said the €2m shortfall was “not a small amount of money” and expressed disappointment that Government funding was not meeting the cost of the roads programme.
Cllr Rita McInerney (FF) said significant road expenditure in areas such as Doonbeg was necessary, adding that “it was required anyway, there was no vanity projects”. She said councillors needed to work closely with the Council to make political representations to Government departments for additional funding.
Cllr David Griffin (FF) said he had spoken with Minister of State Timmy Dooley recently and understood that he was pushing for additional funding. He said the Department of Transport needed to deliver further resources to support local roads.
Responding to the discussion, Chief Executive Gordon Daly said the Council would continue to monitor road expenditure and engage with the relevant Government departments.
He said there had been careful scrutiny of spending throughout the year, but rising inflation and fuel costs meant the Council did not have all the answers regarding the 2027 roads programme.
Mr Daly said the outcome of efforts to secure additional funding for the 2026 programme would influence what could be delivered next year.
He warned that the full programme carried out in 2026 was “not sustainable on a year on year basis”, adding that the Council would continue engaging with Government departments in the new year.