October of next year has been identified as the planned start for the commercial operation of the Synchronous Compensator at Moneypoint.

ESB briefed Clare’s local and national politicians in recent days on the ongoing work for their Green Atlantic plans at Moneypoint.

Four main projects are associated with the development. This includes the Synchronous Compensator on the Moneypoint site, the onshore hub upon which it is planned toconstruct the wind turbine foundations and assemble the wind turbines before floating them to site, the offshore project which will be spread across at least two phases totalling 1,400MW, with the first phase planned for delivery in 2028. The medium term Hydrogen facility onsite which will convert excess offshore wind energy to Hydrogen for storage and other uses is the final project in the plans.

Work on the construction of the Synchronous Compensator is due to commence shortly with the installation of the main equipment from Siemens due to occur in April 2022. Commissioning of the new plant is planned for mid-2022 with commercial operation in October 2022.

When complete, this compensator will be the first in the country and will incorporate the world’s largest flywheel used for grid stability purposes which will promote the connection of greater volumes of renewable energy onto the electricity system.

According to ESB, work on the onshore hub is progressing well with ongoing engagement with Clare County Council and other key stakeholders in the region. The planning application process has commenced with the appointment of an environmental consultant carry out early stage site assessments and long lead ecology surveys. An engineering consultant is due to be appointed imminently to develop a preliminary design.

A socio-economic report assessing the potential job creation and value to the economy of the projected is also to be completed.

Engagement continues with the Department of Energy and Climate Change on the utilisation of ESB’s hybrid connection at Moneypoint and acceleration of plans for floating offshore projects while the overall design for the offshore wind projects is to be finalised with ESB and Equinor.

Members of the project team are currently in the process of reviewing the Government’s recently published documentation on the Maritime Area Planning Bill to ascertain its implications for plans at Moneypoint.

Related News

violet anne wynne
Ex Clare TD Wynne says she can't pay €6.5k debt as she has no income
lifebuoy
We never know when they're needed' - request for audit of lifebuoy stock in Ennis
2
JJ Spaun's gritty triumph at the US Open
hospital bed carer
600 acute beds required in region adding weight to call for new hospital

Advertisement

Latest News
violet anne wynne
Ex Clare TD Wynne says she can't pay €6.5k debt as she has no income
lifebuoy
We never know when they're needed' - request for audit of lifebuoy stock in Ennis
2
JJ Spaun's gritty triumph at the US Open
hospital bed carer
600 acute beds required in region adding weight to call for new hospital
veronica byrne 1
'It embodies the spirit of togetherness' - preparations continue for Relay for Life
Premium
hospital bed carer
600 acute beds required in region adding weight to call for new hospital
cdsl agm 20-07-23 28 donal magee
Magee to succeed Ryan as CDSL Chair
road to nowhere 16-06-25
Idle Road to Nowhere blocking development of 260 homes in Ennis
judge mangan 1
Ennis man (44) appears in court for punching retired judge aged in his eighties
ennis st patrick's day parade 17-03-24 together for palestine 1
'We need to call people out' - Fianna Fáil Cllrs slam Government over Israeli war bonds

Subscribe for just €3 per month

If you’re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.

Subscribe for just €3 per month

If you’re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.

Advertisement