PROJECTS APPROVED for Active Travel in West Clare are not dependent on route selection for the Greenway, senior engineers in Clare County Council has confirmed.

Thirteen projects secured funding under Active Travel in the West Clare Municipal District last year, none of which have been completed fully.

Pedestrian bridges for Cree, Doonbeg, Cooraclare and Inagh remain at the design and feasibility stage with construction due to begin in either 2023 or 2024 according to acting senior executive officer in the West Clare MD, John Oโ€™Malley.

Eleven different areas were selected for footpath works under the scheme. Works in Doonbeg, Kildysart and Labasheeda are completed, Connolly and Quilty near completion, Kilmihil is two thirds of the way there, both Kilrush and Kilkee are said to be sixty percent completed, works have commenced in Cross, Carrigaholt and Kilbaha while Kilmaley is due to commence construction imminently. Miltown Malbayโ€™s footpath works fall under a different category of the funding but are eighty percent complete.

Footpath and lighting work from Ennistymon to Lahinch is not finished, all of the footpath works are done but approval has yet to be received from the TII to install lighting on the Miltown Rd.

In Doolin, the pedestrian crossing at Fitzโ€™s Cross had a planned completion for the second quarter of 2022. A section of footpath between the Cross and Roadford is to be completed in the third quarter of this year subject to the obtaining of landowner agreements.

There are three phases to the footpath works in Spanish Point, the first of which is underway since April, the second is scheduled to commence in May or June with all works to be finished by the end of the year.

Five pedestrian crossings are to be installed in Lisdoonvarna as part of Active Travel funding, footpaths will be linked as well, work was scheduled to begin in the second quarter of this year.

Progress of the West Clare Greenway will confirm the key link points and further designs required for the Cappa Pier to the Marina works. Officials have said their target is to begin construction in 2023 or 2024.

Similarly, the Greenway is to influence the cycleway from Cregg Beach in Lahinch, no target date has been issued as of yet.

Kilkeeโ€™s mobility plan in the vicinity of the Strand Line and Bandstand is at the feasibility stage.

A walkability audit in Kilrush is over three quarters of the way completed.

Detailed design and the securing of tenders are ongoing for the footpath improvements in Lissycasey with works said to be fifteen percent completed.

Both Boston and Ruan fall under the one project for pedestrian works, the Boston crossing is finished with the Ruan equivalent underway since March.

Oโ€™Malley stated that the programme was for five years of funding and commenced last year. It involves โ€œworks of varying complexities with some of the more straightforward works such as footpath upgrades significantly progressed and other works that require landowner consents, environmental assessments, etc. progressing through the appropriate stagesโ€.

An update had been sought by Cllr Shane Talty (FF). โ€œThere is queries regularly with funding announced for projects last summer but are still on the groundโ€. He observed, โ€œcertain elements seems to be contingent on the Greenwayโ€™s development, the lighting on the Miltown Malbay Rd in Lahinch can it be progressedโ€.

โ€œItโ€™s not dependent on the Greenway for the lighting on Miltown Rd, weโ€™re waiting on TII approval and hopeful to get that this year and progress that. It is not impacted in anyway by the Greenway,โ€ senior executive engineer, Enda MacNamara replied.

On the subject of Active Travel, Cllr Ian Lynch (IND) flagged the need for more charging points for electric vehicles. โ€œWe need to think ahead before planning Active Travelโ€. He revealed that one individual in Kilrush made โ€œthe effort to switch to an electric vehicleโ€ but due to the shortage of charging points in the West Clare town they have since reverted to a diesel car. โ€œWe have to up our game on charging points,โ€ Talty agreed.

Related News

windfarm
Last-minute decision to cancel oral hearing for South-East Clare wind farm slammed
Press release-4
Enable Ireland open โ‚ฌ1.2m residential respite service in Barefield
neil nolan 1
Kilkee's Nolan appointed Asst Chief of Staff with Defence Forces
sinead o'donoghue 1
Council hire LDA's O'Donoghue in bid to accelerate housing activation
Latest News
Press release-4
Enable Ireland open โ‚ฌ1.2m residential respite service in Barefield
mike hanrahan song
Liveline closes for Stockton's Wing
neil nolan 1
Kilkee's Nolan appointed Asst Chief of Staff with Defence Forces
o'callaghans mills v abbeydorney 02-11-25 seรกn boyce gary cooney 1
Mills show 'serious resilience' with Doyle optimistic county call-ups await some of his charges
sinead o'donoghue 1
Council hire LDA's O'Donoghue in bid to accelerate housing activation
Premium
Council hire LDA's O'Donoghue in bid to accelerate housing activation
Shortest Clare GAA meeting in decades with business wrapped up in eight minutes
Offshore energy progress off Shannon Estuary 'will be slower than people thought but we must build blocks like stronger West Clare road network'
Qualifying for Munster final has ร‰ire ร“g in 'dreamland'
At least three new officers to join Executive of Clare GAA

Subscribe for just โ‚ฌ3 per month

If youโ€™re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just โ‚ฌ3 a month (less than 75c per week), and thereafter โ‚ฌ8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.