Plans for the development of Doolin Pier are to be put before An Bord Pleanála by the end of this year.

A visitor services building is to be constructed at Doolin Pier as part of the plans which also focuses on enhancements of the public realms and improvements to transporting between the pier and the village.

Additional lands are required for the proposal and therefore approval must be obtained from An Bord Pleanála to acquire them compulsorily.

Seán Lenihan of Clare County Council’s project management office acknowledged that the project “got complicated as it was tied in with the visitor strategy”. He added, “If we tried to do everything at the one time we would get nothing done”.

Works has been completed on the layout of the building and car park but Lenihan flagged that the wastewater treatment for the building must be looked at. He detailed that it is intended to submit the project before An Bord Pleanála in October.

Related News

Pupils and Ms Gráinne Conlon at Leinster House with TD Joe Cooney
O’Callaghan’s Mills NS could become East Clare’s first Gaelscoil
McKernan_Building_Landscape
Colour, cake and clatter in Tuamgraney
FF4BF70A-D2ED-447C-8B05-BCD17181ADE8
Meet the Maker: Keeping the art of goldsmithing alive in County Clare
breast check unit 28-10-26 1
Over 6,000 signatures on petition to keep BreastCheck unit in Clare
Latest News
McKernan_Building_Landscape
Colour, cake and clatter in Tuamgraney
FF4BF70A-D2ED-447C-8B05-BCD17181ADE8
Meet the Maker: Keeping the art of goldsmithing alive in County Clare
breast check unit 28-10-26 1
Over 6,000 signatures on petition to keep BreastCheck unit in Clare
jj ruddles 2
All jobs to be kept as Zest ends catering contract with Shannon Airport
Intensive Clare Podcast Pop Art Cover
Level Playing Field Episode 4: 'I didn't realise how many people were playing padel in Clare'
Premium
'It cannot be one rule for Dublin and another for the Mid-West' - Clare TD says additional bed capacity must be used
'It was the worst game we played all year' - Éire Óg rue another premature provincial exit
Late Kelly goal recycles senior football hopes for St Flannan's College
Not to be for Liscannor ladies in Munster Senior B final
Judge gives East Clare man February deadline to pay €36k to former friend & Bodyke teammate
[the_ad id="161204"]

Annual Subscription!

The Clare Echo annual subscription for just €69.99 a year. 

Prefer to pay monthly? Click the monthly option and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. 

Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.