*Raheen Woods has emerged as a preferred route along the Greenway.ย 

A 43km greenway linking Limerick City and East Clare is to be opened up in stages with officials optimistic 95 percent of the land used will be publicly owned.

Contracts were signed four years ago in June 2021 for the Limerick to Scariff Greenway with local elected represenetatives critical that the project lost momentum and direction along the way.

Senior officials in Waterways Ireland have remained committed to the development of the Greenway and expect to lodge planning permission for the first section in the second quarter of 2026.

There are five sections to the proposed Greenway. Section 1 leads from Limerick City to Black Bridge, Section 2 is from Black Bridge to Oโ€™Briensbridge, Section 3 leads from here to Killaloe, Section 4 is from Killaloe to Tuamgraney and the final section is from Tuamgraney to Scariff.

All sections will not be completed in chronological order. Section 2 will be completed first followed by Section 5, Section 1, Section 3 and Section 4. Work will commence on Section 5 once planning is granted for Section 2.

Western regional manager with Waterways Ireland, Brian Treacy briefed elected members of the Killaloe Municipal District with a progress report for the Greenway. He said consultation has occurred for the project but acknowledged โ€œalbeit some time has passed since our last consultationโ€. The 43km Greenway is funded under Transport Infrastructure Ireland guidelines โ€œwhich means we need to follow the TII stepsโ€. Information evenings will be held before planning applications are lodged for various 8-10km sections, he said.

Completion of a TII peer review is the current focus of the project team and they have been working on this for the past nineteen months. โ€œWe have made progress, it is taking time but a lot of this assessment was critical to the project progressing, we have a review meeting to address final issues for December but weโ€™ve got approval from TII to begin a phased deliveryโ€. The peer review is for the entire scheme.

Engineer John Jones โ€œspent a few months in Dublinโ€ having worked on this project โ€œfor yearsโ€ but is now back steering the Greenway. He said the hope for the preferred route of Section 2 will be along the existing Errinagh Canal which he described as โ€œan old disused canal which is about 15km in length, it is at the rear of Thomond Village in UL and it heads all the way to Clonlara villageโ€.

For section three, the preferred route is along the existing regional road from Oโ€™Briensbridge to Killaloe, Jones outlined, this will also include some lands owned by ESB towards Ardclooney.

On section four, he expects that the Greenway will join the new bypass and come out by Two Mile Gate โ€œand head towards Scariff along the regional road, we will go through Raheen Woods or the existing road to Tuamgraneyโ€. Various routes are to be examined, he added, one included going along the banks of Lough Derg with another overhead Ogonnelloe. โ€œWe are looking at utilising publicly owned lands in the first place, weโ€™d envisage 95% of the Greenway will be in publicly owned landsโ€.

Six viewing points will be in situ in East Clare, โ€œbefore you come to Caher, the viewing area is going to be special,โ€ Jones promised.

Treacy said planning authorities are happy with their approach of breaking the Greenway into sections. He explained, โ€œby delivering the project in a phased manner we will see sections of the Greenway open and accessible in a much shorter timeframe. Each phase forms part of the overall 43km Greenway but has its own stand-alone economic benefitsโ€.

Waterways Ireland will develop the planning submission for the section between Black Bridge and Errinagh Bridge. The land is owned by Waterways Ireland and Brian outlined they aim to lodge a planning application in the second quarter of 2026 and โ€œcommence works as soon as planning is granted. The idea is to see something happening on the ground rather than coming back in twelve months to say weโ€™re doing more assessmentsโ€.

Cllr Tony Oโ€™Brien (FF) said it was โ€œgreat to see progressโ€. He noted the โ€œdifficulties along the wayโ€ and questioned if community groups were involved and notified in areas like Oโ€™Briensbridge where they have developed and maintained areas. โ€œWe are in constant communication with groups in the area,โ€ Treacy confirmed.

Further detail on the Section 3 route was sought by Cllr Oโ€™Brien, โ€œWhen you leave the Parteen Weir, youโ€™re coming along ESB lands, the preferred route seems to me to be running adjacent or on the regional road from Oโ€™Briensbridge to Tuamgraney. Are we talking about building a new piece of infrastructure or use existing infrastructureโ€. Treacy replied, โ€œThat is the reason for wanting to get into phased delivery, the devil is in the detail. It is along the phased road. The County Council have said they will work with us, at the moment it is going up the road corridorโ€.

On the impact to landowners, Cllr Oโ€™Brien questioned if there would be โ€œminimum or little or no disruptionโ€ to which Treacy stated, โ€œAs little as possible, CPO is not something we will be going down the road of, minimum or as little as possibleโ€. He said ESB have โ€œoffered up lands to use, there are areas they have concern with but also areas they have said we can useโ€. Jones advised, โ€œA number of landowners in the area have approached us who have said they will engage with us if we do have difficultiesโ€.

Remarking that the invite for the briefing had been โ€œout for a while,โ€ Cllr Pat Hayes (FF) stated of Section 3, โ€œit is not going to the top of Ogonnelloe or towards the lake which is disappointing from the aesthetic point of viewโ€ to which Treacy flagged, โ€œCost and land has been prohibitiveโ€. Cllr Hayes added, โ€œWeโ€™re debating the end of the footpath into Tuamgraney and how we finish it, weโ€™ve got โ‚ฌ350,000 to finish it, if we had planned this right, we should have put the footpath to the standard of a greenway from Killaloe to Scariff, Iโ€™d say it cost โ‚ฌ1m and I asked why not bring to the standard of a Greenwayโ€.

On the phased approach, Cllr Alan Oโ€™Callaghan (FF) asked โ€œhow far is it down the roadโ€. Treacy stated, โ€œwe are seeking planning as we go along, the idea is we donโ€™t tie up consultants on the design for the full phase. The planning applications will still reference the whole project and will have standalone merit on its ownโ€.

Black Bridge to Oโ€™Briensbridgeโ€™s section will have a construction period of three to four months if successful with planning, Treacy outlined. โ€œWith a fair wind, if we got planning in the middle of next year, Iโ€™d hope that by end of 2027 weโ€™d have phase one deliveredโ€.

Use of public land as much as possible โ€œis encouraging, it is great to connect the heart of Limerick City with the heart of East Clare,โ€ commented Cllr Oโ€™Callaghan. Cyclists and pedestrians will be accommodated with a width of three metres the target along the route.

โ€œ43km would be a nice cycle but it would be a fair long walk of a Sunday,โ€ quipped Oโ€™Callaghan. Officials assured the Kilmurry man that loops would be provided in each section.

Cathaoirleach of the Killaloe MD, Cllr Pat Burke (FG) was confident the Greenway would bring visitors and tourists from Limerick City to East Clare. โ€œInis Cealtra is big visitor attraction but people canโ€™t continue their cycle unless they go to the regional roadโ€.

Adding an additional aspect to the section while the peer review is ongoing โ€œwould add time to where we are,โ€ Treacy replied. He said Waterways Ireland were โ€œfully committed to the Inis Cealtra project as a wholeโ€ and added that when the section to Tuamgraney was built โ€œthere is nothing to say we canโ€™t look at adding another sectionโ€.

Querying the final section from Tuamgraney to Scariff, Cllr Hayes asked, โ€œam I perceiving that you are coming into Raheen and going offroad and a preferred route is to go from the river to Reddanโ€™s Quayโ€ to which Jones confirmed he was correct.

Maghera native Hayes questioned where the section was going off road. โ€œOur preferred route is Raheen Woods back to Tuamgraney, we have to speak to landowners, we have spoken to some, those discussions were previous to this year. When we move forward to more detail, we have to have more discussions,โ€ Jones replied.

โ€œI like the idea of going off-road,โ€ admitted Cllr Hayes. Engineer Jones advised, โ€œIn public consultation thereโ€™s merits in off-road and on-road, we had a number of strong recommendations to stay as close to the road as possible on safety who wanted people near them but thereโ€™s another aspect of wanting to be out in the fresh airโ€.

Officials were asked by Cllr Conor Ryan (FG) if they had conducted an environmental survey. โ€œWe have done a lot of environmental evaluations. We have quite a number of SECs and SPAs in the area, we feel we have a suitable balance got, our own ecologists have looked at this, the next step is to look at each section. We have a lot of the groundwork done,โ€ Treacy replied.

Cllr Ryan then asked if they expected any delays. โ€œI have asked the question of ecologists, they believe we can prepare in three or four months, I canโ€™t guarantee it but it is feasible,โ€ Treacy replied. Detail of the proximity of the greenway to the road was then sought by Cllr Ryan. โ€œWe have to consider flooding and environmental sensitivity, we will try get a balancing act. It will have to be a sensitive balance,โ€ Treacy said.

Senior engineer in the Killaloe MD, Declan Flanagan said, โ€œIt is a good news story that the ball is rolling and we have a piece of infrastructure to deliver. A 43km project is a huge task, it takes a lot of time, it is slow moving progress but it is great to see it coming, it will support Oโ€™Briensbrdge, Killaloe, Scariff and Tuamgraney for coffee shops and visitors to the areaโ€. He asked if an overall estimated timeline was available.

โ€œI can put a tangible timeline on section one because we have the ball rolling,โ€ Treacy responded. โ€œInto the other phases, thereโ€™s landowner negotiation albeit there wonโ€™t be many, I canโ€™t guarantee those and also pinch points along roads that will require agreement. I find it hard to put timeline on full stage, when we get planning for phase one, it will be a different team building it on the ground so the consultant working will go into section two and threeโ€.

Related News

frank landy 1
Businesses 'betrayed' by Council's decision to raise commercial rates by 8%
IMG_3222
Christmas window competition to light up Gort
mullaghmore 1
Burren's hidden wildlife explored in new TG4 series
uhl a&e ward ed 1
More than 350 patients presented to UHL emergency department in 24 hours
Latest News
รฉire รณg v sixmilebridge u21 03-12-25 darren moroney 2
ร‰ire ร“g's excellent year continues as they advance to U21A hurling final
frank landy 1
Businesses 'betrayed' by Council's decision to raise commercial rates by 8%
รกine o'brien rachel healy 1
Nagle elected as Chair at AGM for first time but Healy's exit a blow for Clare LGFA
clare v limerick 21-04-24 peter duggan 1
League fixtures confirmed for Clare's hurlers & footballers
corofin v lissycasey 02-10-22 10 chris maguire
Maguire to referee Munster club football final
Premium
Businesses 'betrayed' by Council's decision to raise commercial rates by 8%
Nagle elected as Chair at AGM for first time but Healy's exit a blow for Clare LGFA
Donal Carey 'a big man in size, warmth, encouragement, vision & how he reached out to people'
Sharing provisional grass cutting schedule would reduce headaches in Shannon
Lifford let victory slip through their fingers in costly draw with Shannon Town

Subscribe for just โ‚ฌ3 per month

If youโ€™re here, you care about County Clare. So do we. Did you rely on us for Covid-19 updates, follow our election coverage, or visit The Clare Echo every week for breaking news and sport? The Clare Echo invests in local journalism and we want to safeguard its future in our county. By becoming a subscriber you are supporting what we do, will receive access to all our premium articles and a better experience, while helping us improve our offering to you. Subscribe to clareecho.ie and get the first six months for just โ‚ฌ3 a month (less than 75c per week), and thereafter โ‚ฌ8 per month. Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.