*The wind farm is located on a 750 hectare site. 

AN BORD PLEANÁLA has given the green light to Coillte for contentious plans for a large scale 19 turbine wind farm in east Clare that will have the capacity to power 66,500 homes annually.

That means that the 110 MW project on the northern western slopes of Slieve Bernagh will have sufficient power to provide electricity to all homes in Clare with recent Central Statistics Office (CSO) census figures confirming a housing stock of 58,148 in Clare.

The wind farm is located on a 750 hectare (1,853 acre) site 4km north-east of the village of Broadford, 7km north-west of the lake heritage town of Killaloe and 2.5km south of the village of Bodyke and straddles seven town lands.

The turbines on the Carrownagowan wind farm have a tip height of 555 ft high and in granting planning permission, the appeals board ruled that the scheme would not adversely affect the integrity of European protected sites.

Documents lodged with the planning application state that the wind-farm will displace 2.825 million tonnes of CO2 over its lifetime, which it described as “a long term beneficial effect”.

The wind farm is to be developed by Future Energy Ireland which is a joint venture between Coillte and the ESB.

The appeals board also concluded that the project would make a positive contribution to Ireland’s strategic policy on renewable energy.

Clare TD, Michael McNamara (IND) claimed however today that the decision creates “a risk of another catastrophic landslide on a site where there were previously landslides accompanying the development of forest roads”.

Deputy McNamara said that he believes that legal challenges will inevitably be mounted against the appeals board grant of permission.

On the issue of potential peat slides, the inspector in the case, Sarah Lynch stated that “peat stability has been examined and I am satisfied that the site does not pose a significant threat to such an event”.

The plan was lodged direct to An Bord Pleanála as it was classified as a Strategic Infrastructure Development (SID) and the appeals board received 21 submissions with the bulk of those opposed to the project.

Ailish and Brian O’Dwyer told the appeals board that there was a significant peat slip in the 1980s in the area and that the lands and depth of peat are not suitable for construction.

Ute and Conrad Rumberger told the appeals board that a previous seven turbine wind-farm was proposed for the area and the reasons for refusal still remain in place.

Donal O’Connor stated that he lives 2km from the proposed development site and argued that the proposal would negatively impact the Heritage Landscape around Lough Derg.

The construction of the wind-farm is to create 100 jobs.

Clare County Council told the appeals board that the principle of the proposed development is in accordance with the policy position of the Council as set out in the Development Plan.

Related News

Ballysheen Graveyard
Elderly visitors facing difficulties at Ballysheen Graveyard over gravel pathways
Section of the R483 in Cree
Safety fears mount over Cooraclare-Cree road ahead of Irish Open
hen harrier 1
Miltown wind turbine with 200 objections appeals failed bid
Outdoor2
Public invited to help shape County Galway’s first outdoor recreation strategy
Latest News
Meelick road speed limit || Insets: Cllr Patrick O'Gorman and Cllr Rachel Hartigan
Limerick-Shannon commuter traffic putting pressure on Clare roads
Ballysheen Graveyard
Elderly visitors facing difficulties at Ballysheen Graveyard over gravel pathways
cratloe vs o'callaghans mills 08-08-26 podge collins 1
Cratloe stun Mills with two injury-time goals to rescue a draw & quench Fireballs
éire óg vs scariff 08-08-26 robert loftus keelan hartigan paul rodgers 1
Loftus inspires Éire Óg seven point turnaround against Scariff
inagh:kilnamona vs st joseph's doora:barefield 08-08-26 david fitzgerald eoghan mcmahon 1
High-flying Inagh/Kilnamona record successive wins at Doora/Barefield's demise
Premium
High-flying Inagh/Kilnamona record successive wins at Doora/Barefield's demise
Kilmaley kick on in second half to push within touching distance of quarter-finals
Sixmilebridge claim derby spoils over Newmarket-on-Fergus
Kildysart must sustain hunger levels & Kilmihil target a more clinical approach
Lissycasey will look to become more ruthless

Annual Subscription!

The Clare Echo annual subscription for just €69.99 a year. 

Prefer to pay monthly? Click the monthly option and get the first six months for just €3 a month (less than 75c per week), and thereafter €8 per month. 

Cancel anytime, limited time offer. T&Cs Apply. www.clareecho.ie.